桩基施工对临近 110kV 高压电缆的影响分析及纠偏方法

打开文本图片集
中图分类号:TM75 文献标志码:A 文章编号:2095-2945(2025)28-0123-04
Abstract: Nowadays, few people have studied the construction protection of 110kV high-voltage cable trench and drag pipe. Basedothepilefoundationconstructionofacertainplot,thispaperanalyzestheimpactofvariouspilefoundationconstruction oncabledisplacementandsurfacesetlementbyembedding cabledisplacement monitoring devicesandarranging surface setlementmonitoringpoints.Theresultshowthatthereisagoodcorrelationbetweensurfaceselementandcabledisplacement, which providesa basis for subsequent rectification technology for high-voltage cableslurry bag expansion.
Keywords:pilefoundation construction;110kVhigh-voltage cable;slurrypocketexpansiongrouting;impactanalysis; rectification method
电力设施保护区涉及地上架设或地下敷设电力管线,根据国网杭州供电公司运检中心发出的告知书“1、人身、材料及施工机械(混凝土泵车、吊车、塔吊、起重机)与高压电缆终端安全距离: 35kV 线路 4m 110kV 线路 5m,220kV 线路 6m;2 、开挖、钻探、打桩、拔桩等施工与高压电缆及通道安全距离:管沟 2m ;非开挖拖拉管 25m (过三级及以下航道 50m ;过二级及以上航道 100m )”。(剩余3975字)