江苏句容抽水蓄能电站地下厂房顶拱施工关键技术

  • 打印
  • 收藏
收藏成功


打开文本图片集

中图分类号:TV731.6 文献标志码:A 文章编号:2095-2945(2025)25-0181-04

Abstract:Inviewof thegeologicalconditionsandconstruction influencingfactorsoftheundergroundpowerhouseof Jurong Pumped Storage Hydropower Station,technical measuressuchasscientificall arranging theexcavationsequencebeforeexcavation, rationallyarrangingconstructionchanels,timelyfollo-upsupportduringthblastingexcavationprocess,ndefectivelyadopting safetymonitoringmeanshavebeenadopted,theexcavationandconstructionprogressofthepowerhouseundercomplexgeological conditionscanbeefectivelyguaranteedandthedeformationofsurroundingrockcanbeefectivelycontrolled,accumulating experience for the excavation and construction of similar underground powerhouse.

Keywords:underground powerhouse;toparch;key technologies;hydropower station;complex geological conditions

句容抽水蓄能电站位于江苏省镇江市,为一等大(1)型工程,电站装机容量 1350MW(6×225MW) ,日蓄能量 607.5×104kWh ,多年平均抽水电量 18×108kWh 。(剩余5177字)