深基坑通长型GFRP筋杆体施工关键技术与性能研究
Study on Construction Key Technology and Performance of GFRP Bar Body in Deep Foundation Pit

打开文本图片集
(,)
中图分类号:TU47 文献标志码:A 文章编号:1005-8249(2025)01-0069-05
DOI:10.19860/j.cnki.issn1005-8249.2025.01.014
( , 1OOO28, China)
Abstract:Inorder toimprove theconstructionapplicationefectoffull-length glassfiberreinforcedplastic(GFRP)bars in deepfoundationpitengineeingundercomplex stressinfluence,the keyconstruction technologiesand performanceof fulllength GRPbars indepfoundationpitengineeringarestudied.Theanchoringendofthefull-length GFRPreinforcementrod adoptsanew typeofclip,anda pressureplateisadded totheanchoring body.Calculatetheeccentriccompresive bearing capacity ofGFRPeinforcementinthe normalsection,obtainthequantityandspecificationsoffull-length GFRPreinforcement required forthecurrentsupportarea,andensure thesupport efectTheresults indicatethatthe32mmdiameterreinforcement rodburstwhensubjected toatensileforceofapproximately1OOOkN.Themaximumdisplacementofthefoundationpitwallat 6m is about 15mm. The optimal clamp hardness is determined to be 80% of GFRP hardness and the optimal anchor thickness is 6cmbasedon stress cloudimages andloaddisplacementdata.Theconstructiontechnologystudied has godapplication ffects in supporting construction.
Key words: deep foundation pit;glass fiber reinforced plastic; full-length;anchor support;coupler
0 引言
深基坑开挖后,坑壁土体失去了原有的支撑,在自身重力和周边土体压力作用下,有变形坍塌的风险。(剩余10171字)