工程土方量计算与调配关键技术研究


打开文本图片集

摘  要:土方工程是土木工程施工的主要工作之一,其工程量的大小、量的合适程度直接关系到下一步工程的施工实施方案、工程施工量、工程决算费用、工程进度和工程质量。该文以土方工程施工的基本原理,重点阐述场地设计标高的确定、场地土方量计算及土方量调配等关键技术,有效降低劳动强度,控制经济效益。

关键词:土方工程量;计算与调配;关键技术;场地设计标高;土方调配量计算

中图分类号:TU751      文献标志码:A          文章编号:2095-2945(2023)19-0189-04

Abstract: Earthwork is one of the main works of civil engineering construction, and its quantity and suitability are directly related to the construction implementation plan, project construction quantity, final account cost, project progress and project quality of the next project. Based on the basic principle of earthwork construction, this paper focuses on the key technologies such as the determination of site design elevation, site earthwork calculation and earthwork allocation, so as to effectively reduce labor intensity and control economic benefits.

Keywords: earthwork quantity; calculation and allocation; key technology; site design elevation; earthwork allocation quantity calculation

在土方工程施工之前,必须要对土方工程量进行科学计算,以此核定土方工程的施工实施方案。(剩余2849字)